Week of |
Schedule |
August
23, 2010 |
Clearing
Limits of Phase 1A
Plan
Flagged in Field – 8-23-10
Meeting
with Adjoining Burgundy Woods HOA – 8-25-10
|
|
|
August
30, 2010 |
Final
Site Plan Approval – Approved 8-30-10
Site
Development Permit Issued 9-1-10
Meeting
with Governor's Grove HOA – September 1, 2010
|
|
|
September
13, 2010 |
Application
for VDOT Entrance Permit – 9/14/10
Initial
Pre-Construction Meeting to Review Clearing Limits –
Walk
of Clearing Limits for Phase 1A Erosion Controls with Fairfax County and
Urban Forestry – 9/15/10
Initiate
Phase 1A Tree Protection - 9/17/10
Site
walk with Burgundy Woods & Governor's Grove HOA – 9/18/10 |
|
|
September
20, 2010 |
Complete
Phase 1A Tree Protection Installation – 9/23/10
|
|
|
September
27, 2010 |
Meeting
with Burgundy Civic Association – 9/27/10
Inspection
by Fairfax County of Tree Protection Measures – 9/29/10
|
|
|
October
4, 2010 |
Received
VDOT Entrance Permit 10/4/10
Initiate
Clearing Operation Onsite to Install Phase 1A Erosion Control Devices |
|
|
October
25, 2010 |
Complete
Phase 1A Clearing and Schedule Inspection
Receive
Final Inspection by Fairfax County of Erosion Control Devices
Special
Inspection Meeting for H-Pile
Building
Permit Issued 10/28/10 |
|
|
November
8, 2010 |
Initiate
installation of H Piles – 11/9/10
Install
Water Monitoring Wells – 2 Wells Installed |
|
|
December
6, 2010 |
Lower
H-Pile Wall 50% Complete |
|
|
January
3, 2011 |
Complete
Lower H-Pile Wall |
|
|
February
7, 2011 |
Complete
upper H Pile Wall Installation
Receive
Final Certification by Geotech Engineer of H Piles
Flag
Clearing Limits for Phase 1B Erosion & Sediment Control Devices |
|
|
February
14, 2011 |
Hold
Pre-Construction Meeting prior to Installation of Phase 1B Tree Protection and
Erosion Control Devices. Initiate Phase 1B Clearing |